COMPLEXITYThis intensive 22-month project, included the demolition and renovation of water systems in this hospital main wings A, B, D and Out-buildings 5 and 6. The project required a two-shift capacity with both day and night operations. The project included multiple trades working on multiple floors simultaneously. The team methodically schedule user groups and patients to temporary leave the work area or to have work with infection controls built around them. This project also included carpentry, acoustical ceiling tile, flooring, access panels for both new construction and renovation.
AWESOME SAUCE QUOTE OR STATISTIC
The Federal Government Awarded Richard Group with ‘Exceptional Ratings’ for Quality, Schedule, and Management, while finishing three months ahead of schedule and zero safety incidents on over 43,000 man-hours of two shift capacity work. This was Richard Group’s first Federal Project.