COMPLEXITYThis new Design-Bid-Build Elevator and Penthouse Upgrade project has more than 40 tradesmen over course of the project. The 18-month period required a long 16-18 procurement of elevator motors and controllers. Richard rebuilt the schedule for two and three crews to retrofit 2-3 elevators at a time along the critical path. This project is highlighted by the performance of multiple trades, DIV 02-28, to include metal fabrication, rough carpentry, finish carpentry, roofing, metal and wood doors, metal framing, resilient flooring, painting, signage, wet-pipe sprinkler, DIV 14 specialty conveying/lifts, plumbing, Direct Digital Controls, HVAC, electrical distribution, communications, physical access control, video surveillance, fire detection and alarm.
AWESOME SAUCE QUOTE OR STATISTIC
More than 100 tradesmen for 24 months without a single lost-time incident with 13 retrofitted elevators across five different campus buildings.